SIA 118/262:2004 – General Conditions for Concrete Construction Overview
The standard SIA 118/262:2004 (Swiss Standard SN 507 262) defines the general conditions for concrete construction in Switzerland. Issued by the Swiss Society of Engineers and Architects (SIA), it belongs to the Allgemeine Bedingungen Bau (ABB) series. This edition replaced the organizational parts of several older standards, including SIA 162 (1993), SIA 220 (1992), and SIA 320 (1978). It serves as a regulatory supplement to the framework established by SIA 118 (General conditions for construction work), specifically for contracts involving concrete and steel-concrete composite structures.
The regulatory scope encompasses the formation, content, and management of contracts for structural concrete work. It governs activities ranging from tendering and bidding to quality management and measurement. The document defines essential roles such as the Bauherr (client/owner) and the Unternehmer (contractor), and introduces specific technical terms like Gesamtleiter (project manager), Kontrollplan (control plan), and Prüfplan (testing plan). It aligns with the technical requirements of SIA 262 (Concrete Construction) and SIA 264 (Steel-Concrete Composite Construction).
This document provides structured rules for specialized tasks, including formwork selection, reinforcement installation, and prestressing systems. It outlines the specific obligations of each contracting party during the preparation and execution phases of a project.
Contractual Basis and Tendering
The standard establishes the hierarchy of contract components. According to Art. 7 and Art. 21 of SIA 118, this standard belongs to the group of other SIA standards. In cases of conflict, the rules of SIA 118 generally take precedence. The tendering process (Ausschreibung) is governed by specific rules:
- §1.1.4: Special provisions for the project may be structured according to the Normpositionen-Katalog (NPK) 102.
- §1.1.7: General measurement surcharges in the bill of quantities should be avoided; difficult or non-quantifiable tasks require separate items.
- §1.2.1: The contractor must provide static calculations for temporary structures like Lehrgerüste (falsework) and scaffolding.
Quality Management and Responsibilities
The document identifies three levels of Quality Management (QM) requirements (Stufe I to III), which must be defined by the client based on project complexity.
- Kontrollplan: The client is responsible for creating a control plan to define the scope and timing of quality checks.
- Prüfplan: The contractor must develop a testing plan to document the required quality of materials and components.
- §1.4.6: If a contractor fails to implement contractually agreed quality assurance measures, the client may intervene after setting a deadline.
Concrete Construction and Formwork Types
The special part (Besonderer Teil) details the execution of concrete work, categorizing formwork and surface finishes to ensure objective measurement and payment.
- Type 1: Normal concrete surface without specific structural requirements.
- Type 2: Concrete surface with a uniform structure.
- Type 3: Fair-faced concrete with a board structure (Sichtbetonoberfläche mit Brettstruktur).
- Type 4: Fair-faced concrete with a panel structure (Sichtbetonoberfläche mit Tafelstruktur).
Measurement rules for formwork include distinctions between vertical, horizontal, and curved surfaces, as well as specific treatments for recesses and joints.
Measurement and Remuneration Rules
Remuneration is based on the contractually agreed bill of quantities. SIA 118/262 provides standard practices for measuring concrete volumes and steel weights.
- §8.5.2.2: For wall and slab formwork, openings with an area of ≤ 2.0 m² are measured as through (not deducted).
- §8.5.3.1: Reinforcement steel weight is determined using the cleaned iron list and a specific weight of 7850 kg/m³.
- §8.4.6.3: Special measures for temperatures below +5°C or above +30°C are paid separately.
Frequently Asked Questions
What happens if there is a conflict between SIA 118 and SIA 118/262?
According to section 0.2, the general standard SIA 118 takes precedence over SIA 118/262 in the event of a contradiction.
How long is the standard concrete curing period?
Unless otherwise specified, section 8.2.5 stipulates a curing period (Betonnachbehandlung) of 5 days, including the leveling of surfaces up to 5% inclination.
Are small recesses deducted from the concrete volume?
No, per section 8.5.5.3, recesses, slits, and inserts with a volume ≤ 0.10 m³ are not deducted from the total concrete volume.
Who is responsible for designing the scaffolding and falsework?
Section 1.2.1 states that static calculations and plans for construction equipment, falsework (Lehrgerüste), and scaffolding are the responsibility of the contractor.
How is reinforcement steel measured?
Reinforcement is typically measured by weight based on the bending list (Eisenliste) using a standard density of 7850 kg/m³.
What are the four formwork types defined in the standard?
Anhang C defines Type 1 (Normal), Type 2 (Uniform structure), Type 3 (Board structure fair-faced), and Type 4 (Panel structure fair-faced).