Beleidsregel Klimaatadaptief Bouwen bij nieuwbouw, gebiedsontwikkeling en herstructurering – Climate-Adaptive Building Policy for Delft
The Beleidsregel Klimaatadaptief Bouwen bij nieuwbouw, gebiedsontwikkeling en herstructurering is a formal policy instrument issued by the Gemeente Delft (Municipality of Delft) in the Netherlands. Effective from October 6, 2022, this document serves as the regulatory framework for integrating climate adaptation into new construction, area development, and restructuring projects. It translates the local Klimaatadaptatie Strategie Delft (2019) and the provincial Convenant Klimaatadaptief Bouwen for South Holland into concrete requirements for spatial planning and development agreements.
The regulation addresses four primary climate-related themes: Extreme neerslag (extreme rainfall), Droogte (drought), Hitte (heat), and Bodemdaling (soil subsidence). It applies to all new-build developments and restructuring projects, defined as the replacement of existing buildings or sites with new structures. The document establishes a hierarchy for water management and sets specific quantitative thresholds for rainwater retention, green surface ratios, and thermal performance of building envelopes. These rules ensure that all new developments contribute to the goal of making Delft climate-resilient by 2050.
The following sections detail the technical standards and design principles required for compliance at both the area (district) level and the individual parcel (lot) level. These standards are evaluated during the plan-testing phase and must be recorded in written agreements between the municipality and developing parties.
Extreme Rainfall and Water Management
The policy establishes a priority sequence for managing rainwater: Groen (green surfaces first), Vasthouden (retention), Bergen (temporary storage), and Afvoeren (drainage) only as a last resort. New developments must be fully disconnected from the municipal wastewater sewer system.
- Area Level (Gebiedsniveau): Critical infrastructure and main roads must remain accessible during a rainfall event of 90 mm per hour, with a maximum of 10 cm of water on the street. The project area must be able to temporarily store a rainfall event of 70 mm per hour for a duration of 24 to 48 hours.
- Parcel Level (Perceelniveau): Individual lots must process 70 mm of rain per hour on-site. Additionally, 90% of the annual rainfall volume (approx. 800 liters per m²) must be infiltrated or reused locally.
- Storage Requirements: Peak storage solutions must be coordinated with the Hoogheemraadschap van Delfland and the municipality.
Drought Mitigation and Soil Sponge Strategy
To prevent structural damage to foundations and maintain healthy greenery, the 'City as a Sponge' principle is applied. The aim is to minimize groundwater depletion by maximizing local infiltration of precipitation.
- Infiltration Targets: 90% of the annual rainfall must be infiltrated into the ground to maintain groundwater levels, depending on specific soil composition.
- Water Buffer: A minimum of 200 liters of water per m² of greenery must be available during the two driest summer months to prevent soil subsidence and ensure plant survival without using drinking water for irrigation.
- Green Design: Preference is given to 'passive' infiltration through green surfaces and water-permeable materials over technical storage systems.
Heat Stress Prevention and Urban Cooling
The regulation aims to limit the Urban Heat Island (UHI) effect. Standards focus on shadow availability, ventilation between buildings, and the use of heat-reflective materials.
- Proximity to Coolness: Every home must be within 300 meters of a green, shaded area of at least 200 m².
- Plot Greening: At least 50% of the total parcel area must consist of intensive greenery (gardens, green roofs, or green facades).
- Facade Performance: At least 40% of all facade surfaces must be heat-reflective, following BREEAM-NL thermal criteria.
- Active Cooling: Cooling systems for buildings must not vent heat into the surrounding public space; passive cooling and thermal energy storage (WKO) are preferred.
Soil Subsidence and Biodiversity
Developments on subsidence-prone soils must demonstrate cost-effective measures to prevent damage over a 60-year lifespan. Biodiversity requirements are governed by a separate document, but the climate policy mandates a direct link to nature-inclusive building.
- Monitoring: Soil subsidence must be monitored for a minimum period of ten years following development.
- Nature-Inclusive Construction: Compliance with the Nota Natuurinclusief bouwen en ontwikkelen is required for all new builds to complement climate adaptation efforts.
Frequently Asked Questions
What is the maximum allowable water depth on roads during extreme rain in Delft?
Main roads and critical infrastructure must remain accessible for emergency services with a maximum water depth of 10 cm during a 90 mm per hour rainfall event.
How much of a new building's parcel must be green space?
At least 50% of the parcel area must be covered by intensive greenery, which can include gardens, green roofs, and green facades.
What is the distance requirement for shaded public spaces in Delft?
Every dwelling must be located within 300 meters of a green, shaded area that is at least 200 m² in size.
Is use of drinking water for irrigation allowed in new developments?
The water supply for greenery must be designed such that the use of drinking water for irrigation is not necessary, typically via a 200 liter per m² buffer.
What thermal standard applies to building facades?
At least 40% of facade surfaces must be heat-reflective according to BREEAM-NL criteria to prevent local warming.
Are private parcels required to disconnect from the rainwater sewer?
Yes, the policy requires parcels to be fully disconnected from the rainwater sewer and to process up to 70 mm of rain per hour on-site.